9, 167 & 191 Willesden Lane

9, 167 & 191 Willesden Lane

Willesden Lane consists of three separate sites. 

167 Willesden Lane comprises 11 dwellings, 191 Willesden Lane contains 7 apartment dwellings and 9 Willesden Lane is made up of 13 dwellings.

191 Willesden Lane was handed over in its entirety on 6 December 2010.  The Bouygues UK/Warings joint venture team was proud to have successfully completed the project approximately two months ahead of programme with zero snags and zero accidents.

Status

9 Willesden Lane:

  •  Service Avaibility granted 31.01.11

167 Willesden Lane:

  • Dwellings: Handover 17.01.11, all snagging discharged 14.02.11
  • Care units variance: Handover 23.03.11, all snags discharged

191 Willesden Lane:

  • Certificate of Avaibility issued for complete building on 6th December 2010

History

9 Willesden Lane:

  • .Service availability granted 31.01.11

167 Willesden Lane:

  • Dwellings: handover 17.01.11, all snagging discharged 14.02.11
  • Care units variance: Decoration on progress. External ramp works on progress

191 Willesden Lane:

  • certificate of Avaibility issued  for complete building on 6th December 2010

News

167 Willesden Lane Completion Photos June 2011

Photos showing completion of 167 Willesden Lane during June 2011.

191 Willesden Lane Completion Photos June 2011

Photos showing completion of 191 Willesden Lane in June 2011.

9 Willesden Lane Completion Photos June 2011

Photos showing completion of 9 Willesden Lane during June 2011.

RoSPA Occupational Health and Safety Awards 2011

Bouygues UK Brent Social Housing PFI, has won a Gold award in the prestigious RoSPA Occupational Health and Safety Awards 2011.

 

The Gold award was...