August 2011

SPW phase 2 is on its final stages, we have currently 5 subcontractors working to finish their outstanding works,

The two football pitch and tennis court are 85% complete which has given the site a good look, our soft landscaping is progressing and the tree planting will start by the end of next week. Our external hard landscaping is also on its final stage as the tarmac has started. Street furniture and cycle shelters are also 60% complete which would lead to a fast completion once the hard landscape is complete.

Electrical installations are on programme as the main cable has been pulled and the feeder pillar is progressed.

CCTV and intercom connections will take place along with the gate installation by 22nd of August”.

Overall progress of 80% 