- Substructure blockwork 100%
- Oversites 100%
- Superstructure 95%
- Timber roofs 100%
- Waterproofing 100%
- M&E 1stfix 100%
- Drylining 100%.
- 2ndFix all trades 100%
- Decoration 100%
- Finals and Snagging 100%
Barnhill Cottages
Status
History
- Groundworks 90%
- Substructure blockwork 100%
- Oversites 100%
- Superstructure 95%
- Timber roofs 00%
- Waterproofing 100%
- M&E 1st fix 100%
- Drylining 100%
- 2nd Fix all trades 50%
- Decoration 10%
News
Barnhill handed over! |
The Barhnill Cottages site has been handed over on 21st July 2011. The Certificate of Availability has been delivered by the Independant Certifier with only five snaggs which have been cleared on the same day. Works has... |
||
Barnhill Cottages Site Photos June 2011 |
Please see progress photos on site at Barnhill Cottages in June 2011. |