- Civil works completed.
- Windows installation 80% completed.
- 5thfloor waterproofing completed.
- Partition 1stfix up to 4thfloor
- Partition 2ndfix up to 2ndfloor
- Flooring started
Brook Avenue
Status
History
- Civil works 90% completed.
- M&E Embedment works in progress.
- Windows installation 35% completed.
- 5thfloor waterproofing completed.
News
Brook Avenue Site Photos August 2011 |
Please see progress photos on site at Brook Avenue in August 2011. |
||
Ecosite and Green Site Office |
On the 24thJune 2011, the Mall and Brook sites were awarded Ecosite and Green Site Office labels. These schemes recognise achievements in minimisin... |
||
Inovpac |
Following the implementation of a new construction process named NORPAC INOVPAC across all Bouygues France Europe and its subsidiaries in 2010, Bouygues UK made the decision to spread this implementation to the Brent Social... |
||
Brook Avenue Site Photos June 2011 |
Please see progress photos on site at Brook Avenue in June 2011. |
||
RoSPA Occupational Health and Safety Awards 2011 |
Bouygues UK Brent Social Housing PFI, has won a Gold award in the prestigious RoSPA Occupational Health and Safety Awards 2011.
The Gold award was... |