- Facades 98% completed
- Metalworks 90% completed
- External services 90% completed
- Hardlandscaping 50% completed
Block 1-2-3:
- Partition 2ndfix 85% completed
- Final painting on progress
Block 4:
- Partition 2ndfix 90% completed
- Flooring 50% completed
- Kitchen installation 30% completed
Block 4-5-6:
- Partition 2ndfix 40% completed