George Green Schedule & Progress June 2012

Progress in June 2012

Phase 1:

 

• All windows installed

• M&E 1st and 2nd fix ongoing

• Dry lining complete

• Ceiling progressing

• Painting in progress

• All joinery activities ongoing

• ICT cabling started

• Flooring preparation started

• New hub room built

• Sample rooms being finalised

 

Construction in July 2012

Phase 1:

• M&E 2nd fix

• Painting

• Doors and joinery

• ICT cabling

• Flooring

• IPS/vanity

• Jetter wing windows

• Removal of temp-class 1st floor

• Sample rooms complete