Overall progress:
- Block B
- Kitchen installation on going
- Carpet flooring installation (90%)
- Lighting and smoke head installation (100%)
- Cubicles installation complete (13/01/12)
- Sanitary wares installation (85%)
- New door frame installation complete
- Door and ironmongery on going (85%)
- Booster set T&C complete (27/01/12)
- Plant room biomass boiler installation (85%)
- Gas purge system commissioned
- Ductwork installation roof kitchen complete (20/01/12)
- Plant enclosure kitchen roof (complete)
- Facade work on going (80%)
- Block D
- Ceilings small hall complete (28/01/12)
- Skimming coat complete
- Pipework in loft complete (27/01/12)
- Cubicles toilets complete (13/01/12)
- Sprinkler plant room installation (90%)
- Block 2 (nursery/reception)
- Wall tiling complete
- Shower complete
- Wall tiling complete
- Blinds complete
- Signage complete
- Roof AHU connection ductwork complete
- Block 1 (KS1/KS2/main hall)
- Flooring complete (27/01/12)
- Door installation complete (20/01/12)
- Lighting main hall complete (28/01/12)
- Signage installation on going
- Blinds installation complete
- Boards installation on going
- AHU connection on going
- RWHT connection on going
- Plant enclosure complete (26/01/12)
- Guard rails roof complete
- Stair guard rail in stair installation
- External works
- Preparation MUGA on going
- Timber sleeper installation (80%)
- MUGA reduce dig complete
- MUGA type 1 complete
- Preparation type 1 around nursery complete