Gordonbrock Primary School

Gordonbrock Primary School

Bouygues UK is proud to announce that they are the appointed contractor undertaking works at Gordonbrock Primary School.

Gordonbrock will be a mix of New Build and Refurbishment circa 3,500sqm for a value of £9.2 million. Works will be undertaken over a fifteen month period starting on site on 18 December 2010 with a targeted completion of 30 March 2012. The school is being entirely decanted by The London Borough of Lewisham prior to the start of the works.
 
The school will be extended from 2.5FE to 3 FE, and include a Nursery.
 

Status

 Overall progress:

  • Block B
  • Kitchen installation on going
  • Carpet flooring installation (90%)
  • Lighting and smoke head installation (100%)
  • Cubicles installation complete (13/01/12)
  • Sanitary wares installation (85%)
  • New door frame installation complete
  • Door and ironmongery on going (85%)
  • Booster set T&C complete (27/01/12)
  • Plant room biomass boiler installation (85%)
  • Gas purge system commissioned
  • Ductwork installation roof kitchen complete (20/01/12)
  • Plant enclosure kitchen roof (complete)
  • Facade work on going (80%)

 

  • Block D
  • Ceilings small hall complete (28/01/12)
  • Skimming coat complete
  • Pipework in loft complete (27/01/12)
  • Cubicles toilets complete (13/01/12)
  • Sprinkler plant room installation (90%)

 

  • Block 2 (nursery/reception)
  • Wall tiling complete
  • Shower complete
  • Wall tiling complete
  • Blinds complete
  • Signage complete
  • Roof AHU connection ductwork complete

 

  • Block 1 (KS1/KS2/main hall)
  • Flooring complete (27/01/12)
  • Door installation complete (20/01/12)
  • Lighting main hall complete (28/01/12)
  • Signage installation on going
  • Blinds installation complete
  • Boards installation on going
  • AHU connection on going
  • RWHT connection on going
  • Plant enclosure complete (26/01/12)
  • Guard rails roof complete
  • Stair guard rail in stair installation

 

  • External works
  • Preparation MUGA on going
  • Timber sleeper installation (80%)
  • MUGA reduce dig complete
  • MUGA type 1 complete
  • Preparation type 1 around nursery complete

History

 Overall progress:

  • Block B
  • Canopy kitchen installed (04/01/12)
  • First fix M&E services complete in kitchen area (23/12/11)
  • Mist coat on-going (100%)
  • 2nd fix M&E on going (95%)
  • Preparation floor finishes on going (90%)
  • Painting main hall complete (23/12/11)
  • Erection of scaffold around block B (04/01/12)

 

  • Block D
  • Structural amendments small hall on going
  • Main LV panel installed with permanent power
  • Strip out complete

 

  • Block 2 (nursery/reception)
  • Snagging reception classroom
  • BYUK office in nursery classrooms
  • Teleflex installed (04/01/12)
  • Loose furniture delivered: chairs, table etc... (15/12/11)

 

  • Block 1 (KS1/KS2/main hall)
  • Vinyl flooring complete in north block, south block first floor.
  • Flooring in corridor north block and south block first floor complete (23/12/11)
  • Final fix M&E (lighting, radiator) complete in classrooms (23/12/11)
  • Sanitary wares connection complete at 99% (flush button to connect)
  • FFE connection on going (95%)
  • IPS installation second fix complete
  • Start of installation of folding partition (04/01/12)
  • Start of Teleflex installation (04/01/12)
  • Permanent lighting north block (04/01/12)

 

  • External works
  • Installation of timber sleeper Gordonbrock Rd
  • Foundation main stair main hall on going
  • Service area foundation on going
  • Platform MUGA – KS2 on going