Main Events
Stripping out of façades and roof is completed. Demolition of existing slab and structural strengthening work of existing structure are starting.
Progress
Overall Progress (up to 20/03/13);
Phase 1
Completion of outstanding works and snags
Phase 2&3
Demolition of Block C, (Temporary works required to support remaining part of 1st floor slab)
Procurement of remaining package
Preparation of Easter break work: rendering of South and West façade of Block D
Handover of BLE lift (adjacent to Spotlight)
Structural strengthening work starting
Construction next month
Block C: demolition/procurement/Structural strengthening
Bock D: removal of redundant services surface mounted (East façade), rendering