The Mall

The Mall

This project will see the construction of 88 Flats and Maisonettes over 4 floors with basement and 81 car park spaces.

Status

Facade works started on block 1

Block 1

  • Waterproofing completed
  • Skimcoat and partition 80% completed
  • Flooring started

Block 2/3/4

  • Civil works 55% completed

 

 

 

 

History

 

Block 1

  • Infrastructure civil works 100% completed 
  • Superstructure civil works 50% completed 
  • M&E Embedment works in progress

Block 2 3 4

  • Drainage and fondations under 50% completed

News

The Mall Site Photos September 2011

Please see progress photos on site at The Mall in September 2011.

The Mall Site Photos July 2011

Please see progress photos on site at The Mall in July 2011.

Children at The Mall

On the 20thJuly 2011, the team of the Mall site welcomed a group of 41 three to five years old children from the Linsday Park Nursery and their teacher. The nursery which is situated opposite the site has been wit...

Ecosite and Green Site Office

 

On the 24thJune 2011, the Mall and Brook sites were awarded Ecosite and Green Site Office labels. These schemes recognise achievements in minimisin...

Inovpac

Following the implementation of a new construction process named NORPAC INOVPAC across all Bouygues France Europe and its subsidiaries in 2010, Bouygues UK made the decision to spread this implementation to the Brent Social...

The Mall Site Photos June 2011

Please see progress photos on site at The Mall in June 2011.