- Oversite 100%
- All floor beams 100%.
- Brick/Blockwork 100%
- Roof Timbers 100%
- Waterproofing 100%
- Window fixing 100%
- M&E 1stFix 100%
- Drylining 100%
- 2ndFixing all Trades 100%
- Decoration 45%
- Finals and snagging just started
Melrose
Status
History
- Oversite 100%
- All floor beams 100%.
- Brick/Blockwork 100%
- Roof Timbers 100%
- Waterproofing 100%
- Window fixing 100%
- M&E 1stFix 100%
- Drylining 95%
- 2ndFixing all Trades 80%
- Decoration Mist Coating all units.
News
Melrose handed over |
The Melrose site was handed over on the 19th August 2011. |
||
Performance Beyond Compliance for Melrose |
The Melrose site was awarded "Performance Beyond Compliance" by the Considerate Constructors Scheme in July 2011.This site has complied with the Scheme's Site Code of Considerate Practice by achieving... |
||
Melrose Avenue Site Photos June 2011 |
Please see progress photos on site at Melrose Avenue in June 2011. |
||
RoSPA Occupational Health and Safety Awards 2011 |
Bouygues UK Brent Social Housing PFI, has won a Gold award in the prestigious RoSPA Occupational Health and Safety Awards 2011.
The Gold award was... |