Overall Progress:
Strip out & Demolition almost completed, awaiting access to 2 rooms in Easter school break.
Structural works in progress
Construction next month:
Phase 2: Structure alterations, partitions.
The proposed development will be a part New Build, part Remodelling and Refurbishment of Phoenix School as part of the London Borough of Tower Hamlet’s Building Schools for the Future programme.
The 25 month construction works are planned to commence in July 2011 to be completed at the end of August 2013.
Overall Progress:
Strip out & Demolition almost completed, awaiting access to 2 rooms in Easter school break.
Structural works in progress
Construction next month:
Phase 2: Structure alterations, partitions.
Progress in September 2012
Construction October 2012
Phoenix School Site Progress Pictures March 2013 |
Site progress pictures of construction during March 2013. |
||
Phoenix School Newsletter April 2013 |
Newletter distributed to the Neighbours |
||
Phoenix School BREEAM Man 9 Case Study |
|||
Phoenix School Progress Photos September 2012 |
Phoenix School Progress Photos September 2012 |
||
Phoenix School Newsletter September 2012 |
Phoenix School Newsletter September 2012 |
||
Phoenix School Progress Photos August 2012 |
Phoenix School Site Progress Photos August 2012 |