Sir John Cass School

Sir John Cass School

Sir John Cass Foundation and Red Coat School is a voluntary aided, Church of England and multi faith school for 900 pupils aged 11-16 and 560 pupils aged 16-18 (6th Form).

The objective of the new development is to upgrade the existing buildings where required as well as the new build elements.

A new double height entrance space will be created by slotting in a new roof and a facade along Stepney Way.

The drama block to the west will be extended with a 2 storey building which matches the width of the existing building.

The third element is a 5 storey block which will be attached to the existing stair of the main block.

Refurbishment to part of the main building, the major part being refresh only as per control option and brief

The other building will remain untouched other than ICT infrastructure upgrade to meet standard requirements. The external areas are remodelled to provide different types of spaces inclusive of a new MUGA.

Status

Progress in August 2012

 

Improvement works:

  • Façade tiles cleaning
  • Acoustic to recording studio
  • Playground drainage
  • Ventilation system under review and monitoring. Conclusions to be drawn on final adjustments
  • to ventilation rates only permitted in the Summer Break

 

Project transferred to Post Completion Department

History

Sir John Cass School was completed and handed over to the school end of February 2012.

News

Sir John Cass School Shotos October 2011

Please see progress photos on site at Sir John Cass School in October 2011.

Sir John Cass School Shotos September 2011

Please see progress photos on site at Sir John Cass School in September 2011.

Sir John Cass Site Pictures August 2011

Please see progress photos on site at Sir John Cass School in August 2011.

Tower Hamlets School Sites Receive Sustainability in Construction Award

On Thursday 28 July, 4 schools within Tower Hamlets’ school renovation programme were awarded a sustainable development award, the Ecosite label, with a further school due for certification in coming weeks and a firm c...

Sir John Cass Site Pictures July 2011

Please see photos to show progress on Sir John Cass School site in July 2011.

Sir John Cass Newsletter May 2011

Dear Neighbour,

The construction team at Bouygues UK is happy to be updating you on our progress at Sir John Cass Red Coat School project!

The external envelope on the 5 storey block water terraces are almos...

Filter