Main Events
Curtain Wall & Brickwork to Dining Pavilion
Main Building
Roof slab installation
1st fix in Lower & Upper Ground Floor
Roofing to Assembly Hall
Electrical Transformer Installation
North Retaining Wall Installation
External Staircase groundworks commenced
Progress
Overall Progress (up to 16/04/13);
Main Building:
Pile Probing = 100%
Platform / Piling mat = 100%
CFA Piling = 100%
Pile Caps = 100%
TC1 Crane Erection = 100%
Ground Beams LGF = 100%
Internal Drainage LGF = 100%
Hollow-core UGF = 100%
Walls UGF = 100%
Hollow-core 1st Fl = 100%
Walls 1st Fl = 100%
Hollow-core 2nd Fl = 100%
Walls 2nd = 100%
Roof Slab = 20%
Parapets = 5%
Partitioning LGF = 50%
1st fix M&E LGF = 50%
Partitioning UGF = 10%
Assembly Hall:
Pile Probing = 100%
Platform = 100%
External Drainage to rear = 100%
VSC = 100%
Internal Drainage = 100%
Underground M&E Services = 100%
Ground Floor Beams & Slab = 100%
Walls = 100%
Roof slab = 100%
Roof steels = 100%
Roof Covering = 50%
Dining Pavilion:
Pile Probing = 100%
Platform = 100%
VSC = 100%
Internal Drainage = 100%
Ground Beams & Slabs = 100%
Structural Steel = 100%
Metsec = 100%
Roofing = 90%
Curtain Wall = 50%
Windows = 75%
Brickwork = 10%
External Drainage:
Surface Water Network = 100%
Foul Water Network = 100%
Car Park Area:
Complete up to final tarmac course including all external M&E service ducts
Site Installation:
Walkway linking accommodation to main building = 100%
Hoarding = 100%
Turnstile = 100%
Site Cabins = 100%
Haul Road = 100%
Material Storage Areas = 100%
Temporary Services:
2 No. electrical TBS = 100%
Thames Water connection now made for temporary water supply
Permanent Services:
Electrical Transformer installed
Construction
Construction next month
Main Building
Completion of Roof
Completion of Parapets
Commencement of external stair case
Completion of Partitioning to LGF
Commencement of 1st fix UGF
Assembly Hall
Completion of Roofing
Commencement of internal trades
Completion of curtain walling / Windows / Doors
Commencement of Brickwork / Scaffolding
Dining Pavilion
Commencement of scaffold / 1st fix M&E/ Partitioning
CCS
1st visit on 07/11/12 = 36.5 / 40
2nd visit on 12/02/13 = 41 / 50
Green Site Office
Platinum Award
EcoSites Label
Achieved