Progress in November 2012
- 4thfloor walls to cluster blocks
- 4thfloor slab to cluster blocks
- Timber frame to Townhouses
Construction in December 2012
- Completion of Block 3 structural works
- Completion of timber frame to townhouses
- Start Roof waterproofing
- Start ground floor brickwork façade to Block 3 and Towhouses Row B